3-D printing innovation in engineering

Selkirk College and Austin Engineering worked together to create a 3-D printed model of the proposed Corra Linn dam upgrades

by
Left to right: Ben Marken (Selkirk College), Blair Weston (FortisBC), Roger Austin (Austin Engineering), Darren McElhinney (FortisBC), Mary Austin (Austin Engineering) and Jason Taylor (Selkirk College)

Left to right: Ben Marken (Selkirk College), Blair Weston (FortisBC), Roger Austin (Austin Engineering), Darren McElhinney (FortisBC), Mary Austin (Austin Engineering) and Jason Taylor (Selkirk College) — Photo courtesy FortisBC

The Corra Linn dam is due for an upgrade.

The current Corra Linn hydroelectric dam on the Kootenay River was built in 1932. FortisBC owns, operates and maintains the dam. The upgrade will include replacing 14 spillway gates and reinforcing the existing structure. The project is expected to be completed by 2021 with a total cost of $63 million.

To showcase the scope of the project, it is important to note that the dam does more than generate electicity for Fortis.

“In addition to power generation, the Corra Linn dam plays a critical role in controlling the reservoir levels in Kootenay Lake, which protects people, habitat and communities downstream from floods,” said Tanya Laing Gahr, corporate communications advisor at FortisBC. The new gates will meet new seismic criteria as well. “By investing in upgrades, FortisBC can make sure legacy infrastructure like the Corra Linn dam continue to operate safely, reliably and at the lowest reasonable cost to our customers for years to come,” said Laing Gahr.

Creating a 3-D printed model of Corra Linn

Austin Engineering Ltd. (AEL) has worked with FortisBC in the Kootenays in the past.

A 3-D print of the dam

Clean Energy BC awarded Selkirk College and Austin Engineering the Operational Excellence award for their work. — Photo courtesy FortisBC

“We had been experimenting with 3-D printed modelling,” said Mary Austin, director of business development at Austin Engineering. It started with the City of Cranbrook’s Idlewood dam in 2016; AEL was contracted to work on the dam. Although 3-D modelling was not in the scope of the work for that project, AEL decided to test its uses.

Over the course of the project, AEL learned what a valuable tool 3-D printed models could be.

“We were able to save quite a lot of money because we were able to test multiple designs,” said Austin. Saving money also saved time because AEL was able to engage with its clients at the design stage.

“We knew something was working, so we wanted to improve the quality of the printing,” Austin said. AEL approached Selkirk College’s applied research school, specifically the digital fabrication program. AEL had already worked with engineering co-op students in the past. Seeing the benefits for 3-D printed models in engineering, the company hired Ben Marken as its first co-op student from the digital fabrication program.

FortisBC was eager to work with both AEL and Selkirk College to create a 3-D printed model of its upgraded dam design.

“We have a very special relationship with Selkirk College,” said Laing Gahr. Almost half of Fortis's Kootenay-based employees attended the college. “We have spent many years nurturing the relationship as part of our focus on strong community connections in the places we operate,” she said.

Benefits of 3-D modelling

FortisBC wanted to upgrade the gates but also wanted a tool for stakeholder engagement that they could bring into the community to help the community understand the dam.

“This tool provides us with real-time modelling of the Corra Linn dam against numerous factors, which is a powerful tool in portraying project concepts and details to diverse audiences,” said Laing Gahr.

The audience includes FortisBC staff, contractors working on the project, regulators and those providing permits, community members and stakeholders.

“It’s a valuable tool to cost effectively and quickly answer questions about these structures,” Austin said, whether those questions concerned project planning, stakeholder engagement, long-term planning or operational costs. “There were traditional methods to getting to some of these answers, but they were prohibitively expensive.”

Traditional methods also required much more time, while AEL completed the model much more quickly. “Everyone was impressed by the final product,” Austin said.

Commencing Phase 2

“The spillway gates are required to comply with new seismic criteria established by industry standards, guidelines and regulation,” said Laing Gahr. The dam structure is already prepared to withstand a maximum occurrence, but the gates need to withstand a serious occurrence. “Upgrading to these new standards will make sure the spillway gates still operate following the occurrence of the maximum earthquake this area could experience.”

Phase 2 of the project will address these seismic requirements. With the help of UBC Okanagan’s Structural Engineering department, FortisBC and AEL will test and analyze their 3-D models with a water pump on a seismic shake table.

“It’s very practical research that has real effects for everyone involved,” said Austin. “It’s very exciting. We are at the preliminary stages at this point, but going forward, this is something that dam owners are looking at throughout North America.”

Clean Energy BC Operational Excellence Award

Selkirk College and Austin Engineering won the Clean Energy BC Operational Excellence award that was presented at the Clean Energy BC Generate 2017 Conference in Vancouver on November 27.

“When we started this project, we had no idea it would be so successful, let alone recognized,” said Austin. “We really appreciate it, and it’s a great recognition for the work that Selkirk is doing at their digital fabrication program. I think it will add a lot of momentum to the second phase of the project.”

FortisBC, Austin Engineering and Selkirk College are excited about the attention the award brings to the practical uses of 3-D printed modelling in engineering. FortisBC is especially excited about the innovation the project represents.

“This represents our focus on collaborating with educational institutions like Selkirk College in a way that fosters strong regional relationships, encourages innovation and helps develop future FortisBC employees who demonstrate progressive, out-of-the-box thinking,” said Laing Gahr.

As FortisBC, Selkirk College and Austin Engineering continue to showcase the benefits of 3-D printed modelling, other companies are watching closely. Stay tuned to see the results of Phase 2’s seismic testing.

Related articles

Close up of lithium being poured from one gloved hand to another.
Energy, Mines, Technology, Alberta New tech aims to extract lithium from oilfield waste

The demand for lithium, used for electric car batteries, is growing exponentially. New green technology could help extract the mineral from oilfield waste

by Julie Matchett
Chief Russell Myers Ross, vice-chair of the Tsilhqot'in National Government, stands in front of the Nation's new solar farm.
Energy, First Nations, British Columbia New solar farm completed by Tŝilhqot’in Nation expected to generate $175,000 in revenue

The 1.25-MW facility, located near Williams Lake, is the largest of its kind in British Columbia

by Julie Matchett
Nerva Energy's Joshua Lewis accepting his International Energy Innovator of the Year award.
Energy, Global International Energy Innovator of the Year awarded to Canada’s Joshua Lewis of Nerva Energy

The Association of Energy Engineers (AEE) is the leading international awards organization honouring excellence in engineering management and projects

View all Energy articles