Teck reports $2.2B in impairment charges and $2.1B in losses

by Keith Powell
Picture of large bulldozer.

“We are taking significant steps to meet the challenge of low commodity prices,” says Don Lindsay, President and CEO of Teck Resources Limited. — Photo courtesy Kootenay Business

Teck Resources Limited (TSX: TCK.A and TCK.B, NYSE: TCK) (“Teck”) reported adjusted profit attributable to shareholders of $29 million, or $0.05 per share, in the third quarter of 2015. Teck also reported non-cash after-tax impairment charges of $2.2 billion resulting in a third quarter loss attributable to shareholders of $2.1 billion, or $3.73 per share. The impairment charges are non-cash revaluations of assets to reflect lower market expectations of commodity prices.

“We are taking significant steps to meet the challenge of low commodity prices,” said Don Lindsay, President and CEO. “We have reduced costs throughout the company and we’ve raised nearly $1 billion in two streaming transactions. We used a portion of those proceeds to reduce debt by $400 million and our current cash balance of $1.8 billion exceeds our remaining $1.5 billion share of capital required for Fort Hills.”

Highlights and Significant Items

  • Gross profit before depreciation and amortization was $670 million in the third quarter compared with $752 million in the third quarter of 2014.
  • Cash flow from operations, before working capital changes, was $302 million in the third quarter of 2015 compared with $553 million a year ago.
  • Adjusted EBITDA (not including non-cash impairment charges of $2.9 billion) was $389 million in the third quarter. Adjusted EBITDA before final pricing adjustments was $530 million.
  • We recorded impairment charges in the aggregate of $2.2 billion on an after-tax basis ($2.9 billion pre-tax) including $1.5 billion on our steelmaking coal assets, $0.3 billion on copper and $0.4 billion on the Fort Hills oil sands project resulting in a loss attributable to shareholders of $2.1 billion.
  • Our debt to debt-plus-equity ratio was 36% at September 30, and our net debt to net-debt-plus-equity ratio was 32%. Giving effect to the impairments and our recent streaming transaction and debt repayments, our pro forma debt to debt-plus-equity ratio and net debt to net-debt-plus-equity ratios at September 30, 2015 were 35% and 30%, respectively.
  • Subsequent to quarter end, we completed the sale of a silver stream linked to our share of the Antamina mine. Taken together with the gold stream sold from the Carmen de Andacollo Operations which closed during the third quarter, these transactions have increased our cash position by approximately $1 billion.
  • Our cash balance of $1.8 billion as of October 21 is more than our $1.5 billion share of costs required to complete Fort Hills. We also have an additional US$3 billion undrawn credit facility that can be used for general corporate purposes and US$1.2 billion available for cash draws or for letters of credit. We have certain contractual arrangements that may result in us having to issue letters of credit that would utilize substantially all of this US$1.2 billion facility.
  • Our cost reduction program combined with a falling Canadian dollar, lower oil prices, and higher copper grades have contributed to reduce our U.S. dollar unit costs for our products with copper and steelmaking coal unit costs falling by US$0.20 per pound and US$20 per tonne, respectively, compared to last year.
  • In response to steelmaking coal market conditions, our steelmaking coal mines took three-week shutdowns during the third quarter to reduce production and product inventory. In the fourth quarter we expect that production rates will be aligned with sales volumes.
  • We have reached agreements with the majority of our customers for the fourth quarter of 2015, based on a quarterly benchmark of US$89 per tonne for the highest quality product and we expect total sales in the fourth quarter, including spot sales, to be at least 6 million tonnes of steelmaking coal.
  • The Red Dog concentrate shipping season is expected to be completed on October 22 with shipments of 1,048,000 tonnes of zinc concentrate. We expect sales of 200,000 tonnes in the fourth quarter reflecting the normal seasonal pattern of Red Dog sales.
  • Our Quebrada Blanca operation restarted normal production activities in late August after unexpected ground movement in late June caused a temporary shutdown of processing facilities. We expect to produce 38,000 tonnes of copper cathode in 2015, a reduction of about 10,000 tonnes compared to the original plan.

Related articles

Large piece of machinery with person standing in bucket.
Mining Insider, Exploration, Mines, Northwest Territories, Nunavut, Yukon $500,000 federal funding to help promote northern mining at annual conference

The Yukon Mining Alliance will use the funding to help showcase the opportunities in the North at the annual PDAC Conference in Toronto

by Julie Matchett
Geoscience representative discussing info at open house with a man.
Mining Insider, Exploration, Minerals, Mines, British Columbia Geoscience BC targets ‘hidden’ Central Interior copper-gold deposits

The Central Interior Copper-Gold Research series aims to better understand potential deposits, attract investment and encourage exploration

by Julie Matchett
Close-up picture of PDAC Award, showing two stylized white hands holding up a transparent diamond shape printed with PDAC logo.
Mining Insider, Exploration, First Nations, Minerals, Mines, Global PDAC 2020 awards honour industry leaders

The 2020 PDAC Award recipients have been announced, celebrating outstanding achievement in the Canadian and international mining industry

by Julie Matchett
View all Mining Insider articles