News

Etango Construction Early Works Update, December 2025

·
Etango Construction Early Works Update, December 2025

Executive Summary

Bannerman Energy Ltd has delivered a comprehensive construction update for its flagship Etango Uranium Project in Namibia, demonstrating significant progress across multiple work streams in December 2025. The company has successfully scaled its site workforce to over 370 personnel and achieved 51% completion of bulk earthworks, with particular emphasis on heap leach pad construction. Critical infrastructure milestones include the successful manufacture, transport and delivery of the High-Pressure Grinding Rolls tertiary crusher, as well as completion of concrete foundations for both the primary crusher and stockpile tunnel.

The engineering and design phases are advancing according to plan, with the dry plant detailed design now 92% complete following successful completion of the detailed model review. The wet plant design remains in earlier stages at 23% completion as the team focuses on validation test work. Long-term infrastructure development is also progressing, with the permanent water supply pipeline installation reaching 16% completion in its first phase.

CEO Gavin Chamberlain highlighted the project's commitment to working with local Namibian contractors who have demonstrated their ability to deliver to international standards. This approach not only supports the local economy but has proven effective in maintaining project schedules and quality standards. The successful execution of complex concrete pours, including a continuous 1,200m3 pour for the stockpile tunnel base, demonstrates the technical competency of the construction teams.

This construction progress represents a significant milestone for Bannerman Energy as it advances one of the few uranium projects currently under construction globally. The Etango project's development comes at a time of renewed interest in uranium as a critical component of clean energy infrastructure, positioning Bannerman to capitalize on strengthening uranium market fundamentals. The company's disciplined approach to construction management and integration of local capabilities suggests strong execution risk mitigation as the project moves toward production.
🤖

AI-Generated Summary. This was written by a robot, not a human. It may contain errors, hallucinations, or confident-sounding nonsense. Always verify facts against the original source before making any decisions.

Read Original Source

Press Release

Bannerman Energy Ltd (ASX:BMN, OTCQX:BNNLF, NSX:BMN) is pleased to advise of further progress in the construction early works activities at its Etango Uranium Project.

KEY OUTCOMES

  • Early works construction activities tracking to overall budget and schedule:

    • Site contractor workforce progressively increased to over 370 personnel.
    • Bulk earthworks contract progressing well and approx. 51% complete, major focus remains construction of heap leach pads.
    • Blasting, crushing and screening of heap leach drainage aggregate advancing to schedule and on-spec.
    • Phase 1 and Phase 2A concrete contracts placed and commenced, with foundations for both primary crusher and stockpile tunnel already poured.
    • High-Pressure Grinding Rolls (HPGR) tertiary crusher successfully manufactured, transported and delivered to site.
  • Detailed design and procurement activities advancing well:

    • Detailed model review (M2) for dry plant successfully completed; civil and mechanical design for dry plant approx. 92% complete.
    • Wet plant design currently focused on validation test work; detailed engineering of wet plant approx. 23% complete.
  • Long-term infrastructure and utilities supply activities progressing strongly:

    • Phase 1 of permanent water supply pipeline installation approx. 16% complete.

    The first concrete pour at the primary crusher site has been completed. A total of 500m3 was poured at an average flow rate of 40m3 per hour.

    ““The Etango site is now truly abuzz with activity. Across the board, our early works construction and long lead activities are progressing safely and to schedule. This is a direct function of the dedication of both our contract partners and Bannerman personnel. We are continuing to award key contracts to local Namibian contract partners, who have proven their ability to deliver to world-class standards. A particular highlight for the project team over recent weeks was the pouring of the stockpile tunnel base, which was a 1,200m3 continuous concrete pour that was achieved seamlessly.”

Gavin Chamberlain - Chief Executive Officer, Bannerman Energy

The full construction update can be read here.

The post Etango Construction Early Works Update, December 2025 appeared first on Bannerman Energy.

Aggregated Content

This article was imported from an RSS feed. Content and accuracy are the responsibility of the original publisher.