Etango Construction Early Works Update, December 2025
Executive Summary
The engineering and design phases are advancing according to plan, with the dry plant detailed design now 92% complete following successful completion of the detailed model review. The wet plant design remains in earlier stages at 23% completion as the team focuses on validation test work. Long-term infrastructure development is also progressing, with the permanent water supply pipeline installation reaching 16% completion in its first phase.
CEO Gavin Chamberlain highlighted the project's commitment to working with local Namibian contractors who have demonstrated their ability to deliver to international standards. This approach not only supports the local economy but has proven effective in maintaining project schedules and quality standards. The successful execution of complex concrete pours, including a continuous 1,200m3 pour for the stockpile tunnel base, demonstrates the technical competency of the construction teams.
This construction progress represents a significant milestone for Bannerman Energy as it advances one of the few uranium projects currently under construction globally. The Etango project's development comes at a time of renewed interest in uranium as a critical component of clean energy infrastructure, positioning Bannerman to capitalize on strengthening uranium market fundamentals. The company's disciplined approach to construction management and integration of local capabilities suggests strong execution risk mitigation as the project moves toward production.
AI-Generated Summary. This was written by a robot, not a human. It may contain errors, hallucinations, or confident-sounding nonsense. Always verify facts against the original source before making any decisions.
Press Release
Bannerman Energy Ltd (ASX:BMN, OTCQX:BNNLF, NSX:BMN) is pleased to advise of further progress in the construction early works activities at its Etango Uranium Project.
KEY OUTCOMES
-
Early works construction activities tracking to overall budget and schedule:
- Site contractor workforce progressively increased to over 370 personnel.
- Bulk earthworks contract progressing well and approx. 51% complete, major focus remains construction of heap leach pads.
- Blasting, crushing and screening of heap leach drainage aggregate advancing to schedule and on-spec.
- Phase 1 and Phase 2A concrete contracts placed and commenced, with foundations for both primary crusher and stockpile tunnel already poured.
- High-Pressure Grinding Rolls (HPGR) tertiary crusher successfully manufactured, transported and delivered to site.
-
Detailed design and procurement activities advancing well:
- Detailed model review (M2) for dry plant successfully completed; civil and mechanical design for dry plant approx. 92% complete.
- Wet plant design currently focused on validation test work; detailed engineering of wet plant approx. 23% complete.
-
Long-term infrastructure and utilities supply activities progressing strongly:
- Phase 1 of permanent water supply pipeline installation approx. 16% complete.
The first concrete pour at the primary crusher site has been completed. A total of 500m3 was poured at an average flow rate of 40m3 per hour.““The Etango site is now truly abuzz with activity. Across the board, our early works construction and long lead activities are progressing safely and to schedule. This is a direct function of the dedication of both our contract partners and Bannerman personnel. We are continuing to award key contracts to local Namibian contract partners, who have proven their ability to deliver to world-class standards. A particular highlight for the project team over recent weeks was the pouring of the stockpile tunnel base, which was a 1,200m3 continuous concrete pour that was achieved seamlessly.”
Gavin Chamberlain - Chief Executive Officer, Bannerman Energy
The full construction update can be read here.
The post Etango Construction Early Works Update, December 2025 appeared first on Bannerman Energy.
Aggregated Content
This article was imported from an RSS feed. Content and accuracy are the responsibility of the original publisher.
Company Mentioned
Related Stories
NEO Battery Partners with Highest-Ranking ROK Army’s Capital Defense Command for Defense Drone & Robotics Batteries
2 hours ago
Astra Provides Corporate Update, Commences Phase III Drilling at La Manchuria Gold and Silver Project in the Deseado Massif, Argentina
7 hours ago
HONEY BADGER SILVER INC. ANNOUNCES PROMISING HIGH-GRADE GERMANIUM POTENTIAL AT PRAIRIE CREEK FROM RESEARCH PARTNERSHIP
8 hours ago
EMP METALS RECEIVES FIRST SALTWORKS EQUIPMENT DELIVERIES AT PROJECT AURORA DEMONSTRATION PLANT
11 hours ago
Sigma Lithium to Release First Quarter 2026 Earnings Results on May 15, 2026
21 hours ago