News

Etango Construction Early Works Update, March 2026

·
Etango Construction Early Works Update, March 2026

Executive Summary

Bannerman Energy Ltd has delivered a comprehensive progress update on early works construction activities at its flagship Etango Uranium Project in Namibia, demonstrating significant momentum as the project advances toward full construction. The update highlights the substantial scale of current operations, with over 560 contract personnel actively working on site and the achievement of 500,000 lost-time injury-free hours, underscoring both the project's operational significance and strong safety performance.

Construction progress across multiple work streams is tracking well against budget and schedule expectations. The bulk earthworks contract, representing a critical foundation for project development, has reached approximately 66.5% completion with major focus areas including heap leach pad construction and wet plant terrrace development. Concrete operations have achieved meaningful milestones, with 5,509 cubic meters cast for Phase 1 and Phase 2A contracts at key facilities including the primary crusher, stockpile tunnel, and fine ore silo, representing 32% of total concrete volume requirements for these packages.

Engineering and design activities continue to progress systematically, with civil and mechanical design for the dry plant reaching 93% completion and remaining aligned with construction drawing issuance schedules. Wet plant design work is currently focused on layout optimization while maintaining schedule alignment for drawing delivery later this year. Infrastructure development is also advancing, with Phase 1 of the permanent water supply pipeline installation reaching 70% completion.

The comprehensive nature of this update reflects Bannerman's systematic approach to project execution as it approaches a targeted Final Investment Decision later this year. The company's ability to maintain multiple parallel work streams while achieving safety and schedule targets positions the Etango project favorably within the uranium development landscape. With uranium markets experiencing renewed interest driven by nuclear energy expansion and supply security concerns, the visible progress at Etango represents a significant step toward bringing new uranium production capacity online.

For the broader uranium sector, Etango's advancement is particularly noteworthy given the limited number of projects currently in active construction phases globally. The project's scale and the demonstrated execution capability provide important validation for uranium project development in Namibia, a jurisdiction that has emerged as a key uranium production region. As the project moves toward full construction authorization, it represents a meaningful addition to the global uranium development pipeline at a time when new supply sources are critically needed.
🤖

AI-Generated Summary. This was written by a robot, not a human. It may contain errors, hallucinations, or confident-sounding nonsense. Always verify facts against the original source before making any decisions.

Read Original Source

Press Release

Bannerman Energy Ltd (ASX:BMN, OTCQX:BNNLF, NSX:BMN) is pleased to advise of further progress in the construction early works activities at its Etango Uranium Project.

KEY OUTCOMES

  • Early works construction activities tracking to overall budget and schedule:

    • Site contractor workforce now over 560 personnel and 500,000 LTI-free hours achieved on the project to date.
    • Bulk earthworks contract progressing well and approx. 66.5% complete, major focus remains construction of heap leach pads and wet plant terraces.
    • Blasting, crushing and screening of heap leach drainage aggregate advancing to schedule and on-spec with approx. 24% of total requirement completed.
    • Total 5,509m3 of concrete cast as part of Phase 1 and Phase 2A concrete contracts at the primary crusher, stockpile tunnel and fine ore silo. This represents approx. 32% of the volume of concrete to be poured for these packages.
  • Detailed design and procurement activities advancing well:

    • Civil and mechanical design for dry plant approx. 93% complete and aligned with schedule requirement for issue of construction drawings.
    • Wet plant design currently focused on layout optimisation; progress also remains aligned with schedule requirement for issue of construction drawings later this year.
  • Long-term infrastructure and utilities supply activities progressing strongly:

    • Phase 1 of permanent water supply pipeline installation advancing with approx. 70% complete.

    “The Etango site is developing rapidly as construction of the project advances at a visible and impressive pace. The presence of over 560 contract personnel actively working on this initial build program shows the scale and significance of our progress. “We are two thirds of the way through the 24-month bulk earthworks contract, which continues to advance on budget and schedule. Our early construction works activities continue to maintain the critical path for the Etango construction timeline. “The excellent outcome to date is largely due to the quality and dedication of our key contract partners in the delivery of all major programs of work currently in progress. This commitment is matched amongst the Bannerman owner’s team, as Etango continues towards a targeted Final Investment Decision and full-scale construction launch later this year.”

Gavin Chamberlain - Chief Executive Officer, Bannerman Energy

Read the full update here and watch the latest project update video here

The post Etango Construction Early Works Update, March 2026 appeared first on Bannerman Energy.

Aggregated Content

This article was imported from an RSS feed. Content and accuracy are the responsibility of the original publisher.