The M&E DISPATCH // 174

THE DISPATCH
Assemble Here - Lights Back On
A 110-year-old paper mill in northern Ontario just became the staging ground for a $1.8-billion hospital build, a locomotive that hadn't moved since 2014, and the supply chain for the Ring of Fire. And it's not the only one.
In January, a locomotive moved through Iroquois Falls for the first time in twelve years.
Engine DESX 1305, last used in 2014 by Resolute Forest Products, rolled back onto roughly 10 kilometres of track between Porquis Junction and the former Abitibi Paper Mill site. Ontario Northland had finished rebuilding the line three months earlier. The locomotive's return was, in the local mayor's words, the moment everyone in town had been waiting on for more than a decade.
It is also exactly what I want to talk to you about this week.
The site.
The mill that defined Iroquois Falls — and effectively built the town — was founded in the early 20th century by Frank Anson, founder of the Abitibi Power and Paper Company. For nearly a hundred years, the mill was the town's economy. When the paper industry collapsed, the town went with it.
In 2016, a development company called BMI Group bought the site.
They didn't try to make paper again. They didn't tear it down. They re-zoned the strategy entirely.
What they bought:
✅ 144,000 square feet of warehouse space, eight loading docks, two rail bays
✅ 838+ hectares of industrial-zoned land
✅ Storage silos, three-phase power, deepwater proximity, direct rail to the Ontario Northland mainline
✅ A workforce in a town that desperately needed one back
What they spent the next nine years doing was turning all of it into something the resource sector could use.
In May 2025, BMI relaunched the site as Abitibi Connex — a multimodal logistics hub serving the natural resources, agriculture, and food sectors, with reach extending as far north as Hudson Bay.
By July, they had their first anchor tenant.
The first cargo.
That anchor was Pinnacle Logistic Solutions, contracted by Pomerleau Healthcare Partners as the construction logistics provider for the $1.8-billion Weeneebayko Area Health Authority hospital redevelopment in Moosonee and Moose Factory.
Materials are staging at Abitibi Connex and moving north by rail.
A dead paper mill is now the supply chain for the largest hospital build in Canada's far north.
CBC, which visited the site in July 2025, called it "a unicorn facility."
By BMI COO John Veldman's count, they're aiming for 10 to 15 tenants total in the logistics and manufacturing space. One is, in Veldman's words on the record, "in the emerging technologies" — though he was under NDA at the time of the interview and couldn't say more.
The model is bigger than one mill.
Abitibi Connex would be interesting on its own. What makes it a story is that BMI is doing the same thing at six other sites: Bioveld Niagara in Thorold (600+ acres, 1.4 million sq ft, over $1 billion in tenant investment already on site), Red Rock Mill in Northern Ontario (300 acres, being positioned as a critical mineral hub with rail, highway, and deepwater port access, with Rock Tech Lithium publicly tied to the site as a candidate for Ontario's first lithium processing facility), Norderra in Baie-Comeau, Bioveld North in Espanola, Willmarck Mackenzie in BC, and the former Prince Albert Pulp Mill in Saskatchewan, acquired October 31, 2025.
BMI calls it "ready-stating and re-futuring" strategic properties. In plain English: buy the dead mill, clean up the site, restore the rail, plug it back into the ports, and lease the infrastructure to whoever needs to move resources for the next thirty years.
And BMI is not the only one doing it.
Three weeks ago, in Delta, BC — a sleepy stretch of industrial buildings between a plumbing-supply company and a fitness-equipment warehouse — Mangrove Lithium held a ribbon-cutting on North America's first electrochemical lithium refining facility.
Mangrove's founder, Saad Dara, started the company as a thesis project in 2013. The Delta facility went online April 19, 2026. It's a critical-mineral processing operation sitting inside what the CBC described as a "clown building" of unassuming industrial space, in a neighbourhood where the marquee tenants make ladders.
Mangrove has a federal commitment of $21.8 million under the Critical Minerals Research, Development and Demonstration program, announced at PDAC in March. The company has already announced plans for an Eastern Canada facility with the capacity to supply 500,000 EVs annually.
This is the same thesis as Abitibi Connex, just expressed differently. Take an unassuming industrial footprint nobody was paying attention to. Plug critical-mineral economics into it. Turn the lights on.
In Sudbury — sitting on $8 to $10 billion worth of nickel locked inside the city's mine tailings — MIRARCO Mining Innovation is running a 10,000-square-foot pilot facility that uses bioleaching to recover nickel, cobalt, and copper from waste rock.
MIRARCO's CEO, Nadia Mykytczuk, told CBC last month that the technology is proven (it's used at roughly 30 mine sites globally) but Canada has yet to deploy it commercially at scale. Senior scientist Emmanuel Ngoma is recovering 98 to 99 percent of the nickel that goes through the bench-scale process.
This is reactivation of a different kind. Not the building. The material. The tailings ponds around Sudbury are themselves a brownfield asset waiting on the right unlock.
On Vancouver Island, Sasquatch Resources (CSE: SASQ) is going after a more than century-old mine site — but they aren't planning to mine it.
The original Mount Sicker mines produced copper, gold, silver, and zinc, and left behind three main piles totalling roughly 300,000 tons of waste rock — material that was processed and discarded as worthless when the cutoff grades and recovery technology of the day couldn't extract its value. It has been sitting at surface ever since, slowly leaching acid into the surrounding watershed.
Sasquatch's plan: crush the piles, sort out the high-grade sulphides, sell the concentrate, address the open mine shafts (some up to 200 feet deep), and leave the site in better shape than they found it. No drilling. No tailings pond. No new mine.
CEO Pete Smith told me the project is projected to require around $2 million in capital — a fraction of a traditional operation — with cash flow possible within a couple of months of starting and the project wrapping in roughly a year.
I sat down with Smith for a long conversation about how the model works, where the risks sit, and what the path to production looks like for something that doesn't fit any of the usual junior templates. Full interview in an upcoming dispatch.
If the approach holds, British Columbia has an estimated 2,000 legacy mine sites that could be candidates for the same playbook. Mount Sicker would be the proof of concept.
More on this one soon.
Why this matters for you.
In Issue 1, I wrote this:
"We have empty industrial buildings with three-phase power and rail spurs already run to the door."
Abitibi Connex is one of those buildings. So is Red Rock. So is the Delta industrial park where Mangrove is now refining lithium. So is the MIRARCO pilot site in Sudbury.
And the buildings are only half of it. The mine sites are the other half. At Mount Sicker, and at 2,000 other locations across BC alone.
If you're a critical minerals processor looking at a Canadian footprint, the inventory exists. You don't need to greenfield. You need a phone call.
If you're a supplier moving equipment into a James Bay project, Abitibi Connex is the closest deepwater-to-rail node north of Toronto. That isn't a forecast. That's a customer doing it right now for a $1.8-billion hospital build.
If you're a heavy industrial OEM — see Issue 2 — these sites are your assembly inventory.
The buildings have been here the whole time. So have the mines. What's new is that the people running them are finally being met by tenants and operators who need exactly what's already on the ground.
What I'm watching.
A few things that will tell you whether this is a moment or a movement.
The second anchor at Abitibi Connex. Veldman teased "emerging technologies" under NDA. Whoever signs next will tell you how high the site can scale.
The Rock Tech Lithium decision at Red Rock. BMI's own materials still use the word "considering." A signed commitment turns Red Rock from a promising brownfield into Ontario's first operating lithium converter. Until then, it's a candidate.
Mangrove's eastern facility. They have announced it. They have not sited it. When they pick a location, it will instantly become the most valuable industrial postcode within fifty kilometres.
MIRARCO's path to commercial scale. A 10,000-square-foot bench is not a refinery. The question is whether the bioleaching economics survive the jump from pilot to production. The Sudbury tailings are worth $10 billion if the answer is yes.
Sasquatch and Mount Sicker. Pete Smith is advancing a model that could become the template for addressing 2,000 legacy mine sites across BC, with environmental remediation and mineral recovery built into the same project. I sat down with Smith — full conversation in an upcoming dispatch.
The Canada Strong Fund's first brownfield play. Site readiness is exactly the kind of nation-building infrastructure the Fund's mandate covers. The first time it cuts a cheque into a reactivated mill or a legacy mine site is the moment this becomes federal policy in practice, not just a thesis.
The lights are coming back on. The next question is how fast, and how many.
Coming in Issue 4: The Vertical Play
Next edition, I'm going upstream. Or downstream, depending on where you started. A Canadian operator that refused to stay at the wrong end of the supply chain and built the next step themselves.
-Lee
Canada's #1 Mining & Energy Newsletter
Get the briefing.
Twice a week.